Companhia do Metropolitano de São Paulo

Line 2 - Green (Ana Rosa - Tamanduateí)

Contractor:Andrade Gutierrez and Odebrecht

The extension of line 2 - Green represents a significant progress to the Metro network, providing more life quality to the public transport users in Metropolitan Region. In the first part of the work, 3.4 km of line will be built, passing through Chacara Klabin, Imigrants and Ipiranga Stations

Novatecna performed 20,000 m of jet grouting columns in 2005 and will continue to work in 2006 for the conclusion of the first stage and for the remaining 3.4 km of tunnels.


Imigrantes Station - Soil consolidation with ccph

 


Shaft Borghese - Tunnel Portal